Patrick is at this very moment prepping the inside walls for doggy safe, clear wood sealant for the lower eight feet of the kennel walls. I need to figure out new, more visible signs for the street. The actual kennels should be arriving in the coming days, and next week the appliances will be here, the final cement pour should be complete with the sunny weather that we are supposed to be getting, perhaps the septic and drain-field will be done, maybe the driveway topped off and made all pretty, and the fencing should be at least nearly finished. We're really getting there! Although I feel like I'm just asking for it when I say things like that. Can't help it, just getting too excited about completion.
We need to wait for the fire system people, who dropped the ball completely, to finish installing the fire alarm system. They said sometime around January 2nd or 3rd. But if they have a cancellation they might come earlier.
After that we just need final inspections and the occupancy permit.